A English

Time and Work Questions in English

Competitive Exam Quantitative Aptitude · Time and Work and Wages · Time and Work

331+

Questions

English

Language

100%

With Solutions

Showing 50 of 331 questions in English

251
DifficultMCQ
$S, T$ and $U$ can complete a work in $40, 48$ and $60$ days respectively. They received $Rs. 10800$ to complete the work. They begin the work together,but $T$ left $2$ days before the completion of the work and $U$ left $5$ days before the completion of the work. $S$ completed the remaining work alone. What is the share of $S$ (in $Rs.$) from the total money?
A
$4000$
B
$4320$
C
$4500$
D
$4860$

Solution

(D) Efficiency of $S = 240/40 = 6$ units/day.
Efficiency of $T = 240/48 = 5$ units/day.
Efficiency of $U = 240/60 = 4$ units/day.
Let the total work be $240$ units.
Let the total time taken be $x$ days.
$S$ worked for $x$ days,$T$ worked for $(x-2)$ days,and $U$ worked for $(x-5)$ days.
Total work: $6x + 5(x-2) + 4(x-5) = 240$
$6x + 5x - 10 + 4x - 20 = 240$
$15x - 30 = 240$
$15x = 270 \Rightarrow x = 18$ days.
Work done by $S = 6 \times 18 = 108$ units.
Share of $S = (108/240) \times 10800 = 0.45 \times 10800 = Rs. 4860$.
252
MediumMCQ
Raman is $25\%$ more efficient than Aman. If Aman can complete a piece of work in $25$ days,Raman can complete the same work in how many days?
A
$12$
B
$15$
C
$16$
D
$20$

Solution

(D) Let the efficiency of Aman be $100$ units/day.
Since Raman is $25\%$ more efficient than Aman,the efficiency of Raman is $100 + 25 = 125$ units/day.
The ratio of efficiency of Raman to Aman is $125 : 100 = 5 : 4$.
Since time taken is inversely proportional to efficiency,the ratio of time taken by Raman to Aman is $4 : 5$.
Given that Aman takes $25$ days to complete the work,we have $5$ units of time $= 25$ days.
Therefore,$1$ unit of time $= 5$ days.
The time taken by Raman is $4$ units of time $= 4 \times 5 = 20$ days.
253
MediumMCQ
$A$ is $20\%$ more efficient than $B$. If $B$ alone can complete a piece of work in $12$ days,then $A$ alone can complete the same work in how many days?
A
$10$
B
$12$
C
$14$
D
$16$

Solution

(A) Efficiency ratio of $A$ to $B$ is $120:100$,which simplifies to $6:5$.
Since time taken is inversely proportional to efficiency,the ratio of time taken by $A$ to $B$ is $5:6$.
Given that $B$ takes $12$ days to complete the work,we have $6$ units $= 12$ days.
Therefore,$1$ unit $= 2$ days.
Time taken by $A = 5$ units $= 5 \times 2 = 10$ days.
Thus,$A$ can complete the work in $10$ days.
254
MediumMCQ
Sister can bake $50$ cakes in $25$ hours. Sister and Mummy together can bake $75$ cakes in $15$ hours. How many cakes can Mummy bake in $15$ hours?
A
$25$
B
$45$
C
$20$
D
$10$

Solution

(B) Sister's rate of baking: $50 \text{ cakes} / 25 \text{ hours} = 2 \text{ cakes/hour}$.
Combined rate of Sister and Mummy: $75 \text{ cakes} / 15 \text{ hours} = 5 \text{ cakes/hour}$.
Mummy's rate of baking: $5 \text{ cakes/hour} - 2 \text{ cakes/hour} = 3 \text{ cakes/hour}$.
Number of cakes Mummy can bake in $15$ hours: $3 \text{ cakes/hour} \times 15 \text{ hours} = 45 \text{ cakes}$.
255
MediumMCQ
$P$ can do $\left(\frac{1}{4}\right)$ of the work in $10$ days. $Q$ can do $40\%$ of the work in $40$ days and $R$ can do $\left(\frac{1}{3}\right)$ of the work in $13$ days. Who will complete the work first?
A
$P$
B
$Q$
C
$R$
D
Both $P$ and $R$

Solution

(C) To find who completes the work first,we calculate the total time taken by each person to complete $1$ full unit of work:
For $P$: $\frac{1}{4}$ of the work is done in $10$ days. Therefore,the total time taken by $P = 10 \times 4 = 40$ days.
For $Q$: $40\%$ (or $\frac{40}{100} = \frac{2}{5}$) of the work is done in $40$ days. Therefore,the total time taken by $Q = 40 \times \frac{5}{2} = 100$ days.
For $R$: $\frac{1}{3}$ of the work is done in $13$ days. Therefore,the total time taken by $R = 13 \times 3 = 39$ days.
Comparing the total time taken: $P = 40$ days,$Q = 100$ days,and $R = 39$ days.
Since $39 < 40 < 100$,$R$ will complete the work first.
256
EasyMCQ
$A$ carpenter can build a cupboard in $48 \, \text{hours}$. After $12 \, \text{hours}$, he takes a break. What fraction of the cupboard is yet to be built?
A
$0.4$
B
$0.5$
C
$0.75$
D
$0.25$

Solution

(C) The total time required to build the cupboard is $48 \, \text{hours}$.
In $1 \, \text{hour}$, the carpenter completes $\frac{1}{48}$ of the work.
In $12 \, \text{hours}$, the work completed is $12 \times \frac{1}{48} = \frac{12}{48} = \frac{1}{4}$ of the cupboard.
The remaining work to be done is $1 - \frac{1}{4} = \frac{3}{4}$.
Converting the fraction $\frac{3}{4}$ to a decimal gives $0.75$.
257
MediumMCQ
$A$ can do a piece of work in $12$ days and $B$ in $20$ days. If they together work on it for $5$ days and the remaining work is completed by $C$ in $3$ days, then in how many days can $C$ do the same work alone?
A
$10$
B
$9$
C
$12$
D
$15$

Solution

$A$ completes the work in $12$ days, and $B$ completes it in $20$ days.
Taking the Least Common Multiple $(LCM)$ of $12$ and $20$, the total work is $60$ units.
Efficiency of $A = 60 / 12 = 5$ units/day.
Efficiency of $B = 60 / 20 = 3$ units/day.
Combined efficiency of $(A + B) = 5 + 3 = 8$ units/day.
Work done by $(A + B)$ in $5$ days $= 8 \times 5 = 40$ units.
Remaining work $= 60 - 40 = 20$ units.
$C$ completes the remaining $20$ units in $3$ days, so the efficiency of $C = 20 / 3$ units/day.
Time taken by $C$ to complete the whole work alone $= \text{Total Work} / \text{Efficiency of } C = 60 / (20 / 3) = 60 \times (3 / 20) = 9$ days.
258
EasyMCQ
$A$ and $B$ together can do a piece of work in $9$ days. If $A$ does thrice the work of $B$ in a given time,the time $A$ alone will take to finish the work is (in days)
A
$4$
B
$6$
C
$8$
D
$12$

Solution

(D) Let the efficiency of $B$ be $1$ unit/day.
Since $A$ does thrice the work of $B$,the efficiency of $A$ is $3$ units/day.
Combined efficiency of $A$ and $B$ = $3 + 1 = 4$ units/day.
Total work = (Combined efficiency) $\times$ (Total days) = $4 \times 9 = 36$ units.
Time taken by $A$ alone = $\frac{\text{Total work}}{\text{Efficiency of } A} = \frac{36}{3} = 12$ days.
259
MediumMCQ
Ram and Hari can cut $12 \, kg$ of nuts in $2 \, days$. After $5 \, days$, Hari left the work. Ram took $8$ more days to cut the rest of the nuts. If a total of $58 \, kg$ of nuts were cut, the time taken by Hari to cut $10 \, kg$ of nuts is (in days):
A
$1$
B
$2$
C
$3$
D
$4$

Solution

(D) Let $R$ and $H$ be the daily work rates of Ram and Hari in $kg/day$.
Given: $(R + H) \times 2 = 12 \, kg \implies R + H = 6 \, kg/day$.
In $5$ days, they cut: $5 \times 6 = 30 \, kg$.
Remaining nuts: $58 - 30 = 28 \, kg$.
Ram cut these $28 \, kg$ in $8$ days, so Ram's rate $R = \frac{28}{8} = 3.5 \, kg/day$.
Since $R + H = 6$, then $H = 6 - 3.5 = 2.5 \, kg/day$.
Time taken by Hari to cut $10 \, kg$ of nuts $= \frac{10}{2.5} = 4 \, days$.
260
DifficultMCQ
$A$ and $B$ undertake a piece of work for $Rs. 250$. $A$ alone can do that work in $5$ days and $B$ alone can do that work in $15$ days. With the help of $C$,they finish the work in $3$ days. If everyone gets paid in proportion to the work done by them,the amount $C$ will get is (in $Rs.$)
A
$50$
B
$100$
C
$150$
D
$200$

Solution

(A) Let the total work be the least common multiple of $5, 15,$ and $3$,which is $15$ units.
Efficiency of $A = 15 / 5 = 3$ units/day.
Efficiency of $B = 15 / 15 = 1$ unit/day.
Efficiency of $(A + B + C) = 15 / 3 = 5$ units/day.
Efficiency of $C = (A + B + C) - (A + B) = 5 - (3 + 1) = 1$ unit/day.
The ratio of work done by $A : B : C$ is $3 : 1 : 1$.
The total share is $Rs. 250$.
$C$'s share $= (1 / (3 + 1 + 1)) \times 250 = (1 / 5) \times 250 = Rs. 50$.
261
MediumMCQ
Shashi can do a piece of work in $20$ days. Tanya is $25\%$ more efficient than Shashi. The number of days taken by Tanya to do the same piece of work is
A
$15$
B
$16$
C
$18$
D
$25$

Solution

(B) Let the efficiency of Shashi be $100$ units/day.
Since Tanya is $25\%$ more efficient than Shashi,the efficiency of Tanya is $125$ units/day.
The ratio of efficiencies of Tanya to Shashi is $125:100$,which simplifies to $5:4$.
Since time taken is inversely proportional to efficiency,the ratio of time taken by Tanya to Shashi is $4:5$.
Given that Shashi takes $20$ days to complete the work,we have $5$ units of time $= 20$ days.
Therefore,$1$ unit of time $= 4$ days.
The time taken by Tanya is $4$ units of time $= 4 \times 4 = 16$ days.
262
EasyMCQ
$12$ men and $16$ boys can do a piece of work in $5$ days. $13$ men and $24$ boys can do it in $4$ days. Then,the ratio of the daily work done by a man to that of a boy is:
A
$2:1$
B
$3:1$
C
$1:3$
D
$5:4$

Solution

(A) Let the work done by $1$ man in $1$ day be $M$ and the work done by $1$ boy in $1$ day be $B$.
According to the problem,the total work done is the same in both cases.
$(12M + 16B) \times 5 = (13M + 24B) \times 4$
$60M + 80B = 52M + 96B$
Rearranging the terms to group $M$ and $B$:
$60M - 52M = 96B - 80B$
$8M = 16B$
$\frac{M}{B} = \frac{16}{8} = \frac{2}{1}$
Therefore,the ratio of the daily work done by a man to that of a boy is $2:1$.
263
EasyMCQ
$A$ worker can complete a piece of work in $50$ days. On the first day,he works alone. On the second day,one more person joins him,on the third day,one more person joins them,and this process continues until the work is completed. How many days are needed to complete the work?
A
$8$
B
$9$
C
$10$
D
$11$

Solution

(C) Let the total work be $50$ units.
Since one worker completes the work in $50$ days,the efficiency of one worker is $1$ unit per day.
On day $1$,the number of workers is $1$,so work done = $1$ unit.
On day $2$,the number of workers is $2$,so work done = $2$ units.
On day $3$,the number of workers is $3$,so work done = $3$ units.
This follows an arithmetic progression where the work done on day $n$ is $n$ units.
The total work done in $n$ days is the sum of the first $n$ natural numbers: $S_n = \frac{n(n+1)}{2}$.
We need to find $n$ such that $S_n \ge 50$.
$\frac{n(n+1)}{2} \ge 50 \implies n(n+1) \ge 100$.
For $n = 9$,$9 \times 10 = 90 < 100$.
For $n = 10$,$10 \times 11 = 110 \ge 100$.
Thus,the work will be completed on the $10^{th}$ day.
264
MediumMCQ
$A$ does $\frac{2}{5}$ of a work in $9$ days. Then $B$ joined him and they together completed the remaining work in $6$ days. $B$ alone can finish the whole work in (in days):
A
$6 \frac{12}{13}$
B
$8 \frac{2}{11}$
C
$10$
D
$18$

Solution

(D) Step $1$: Calculate the work done by $A$ in $9$ days.
$A$ does $\frac{2}{5}$ of the work in $9$ days.
So,$A$'s efficiency $= \frac{2/5}{9} = \frac{2}{45}$ work per day.
Step $2$: Calculate the remaining work.
Remaining work $= 1 - \frac{2}{5} = \frac{3}{5}$ of the work.
Step $3$: Calculate the combined efficiency of $A$ and $B$.
They complete $\frac{3}{5}$ of the work in $6$ days.
Combined efficiency $(A+B) = \frac{3/5}{6} = \frac{3}{30} = \frac{1}{10}$ work per day.
Step $4$: Calculate $B$'s efficiency.
$B$'s efficiency $= (A+B) - A = \frac{1}{10} - \frac{2}{45}$.
Taking $LCM$ of $10$ and $45$ as $90$:
$B$'s efficiency $= \frac{9-4}{90} = \frac{5}{90} = \frac{1}{18}$ work per day.
Step $5$: Calculate the time taken by $B$ to finish the whole work.
Time taken by $B = \frac{1}{1/18} = 18$ days.
265
MediumMCQ
Akka can bake $100$ cakes in $20$ hours. Akka and Tai together can bake $75$ cakes in $10$ hours. How many cakes can Tai bake in $20$ hours?
A
$25$
B
$50$
C
$30$
D
$75$

Solution

(B) $1$. Calculate Akka's rate of baking: Akka bakes $100$ cakes in $20$ hours,so her rate is $100 / 20 = 5$ cakes per hour.
$2$. Calculate the combined rate of Akka and Tai: They bake $75$ cakes in $10$ hours,so their combined rate is $75 / 10 = 7.5$ cakes per hour.
$3$. Calculate Tai's rate of baking: Tai's rate = (Combined rate) - (Akka's rate) = $7.5 - 5 = 2.5$ cakes per hour.
$4$. Calculate the number of cakes Tai bakes in $20$ hours: $2.5 \text{ cakes/hour} \times 20 \text{ hours} = 50$ cakes.
266
DifficultMCQ
$B$ would have taken $10 \, \text{hours}$ more than what $A$ would have taken to complete a task if each of them worked alone. Working together they can complete the task in $12 \, \text{hours}$. How many $\text{hours}$ would $B$ take to do $50 \%$ of the task?
A
$30$
B
$15$
C
$20$
D
$10$

Solution

(B) Let the time taken by $A$ to complete the task be $x \, \text{hours}$.
Then,the time taken by $B$ to complete the task is $(x + 10) \, \text{hours}$.
Working together,their combined rate of work is $\frac{1}{x} + \frac{1}{x + 10} = \frac{1}{12}$.
Solving for $x$: $\frac{x + 10 + x}{x(x + 10)} = \frac{1}{12} \implies 12(2x + 10) = x^2 + 10x$.
$24x + 120 = x^2 + 10x \implies x^2 - 14x - 120 = 0$.
Factoring the quadratic equation: $(x - 20)(x + 6) = 0$.
Since time cannot be negative,$x = 20 \, \text{hours}$.
Thus,$B$ takes $x + 10 = 30 \, \text{hours}$ to complete the whole task.
To complete $50 \%$ of the task,$B$ will take $50 \% \text{ of } 30 \, \text{hours} = 15 \, \text{hours}$.
267
MediumMCQ
$28$ men can complete a piece of work in $15 \, \text{days}$ and $15$ women can complete the same piece of work in $24 \, \text{days}$. What is the respective ratio between the amount of work done by $30$ men in $1 \, \text{day}$ and the amount of work done by $18$ women in $1 \, \text{day}$?
A
$4:7$
B
$9:15$
C
$3:5$
D
$10:7$

Solution

(D) Let $1$ man's $1 \, \text{day}$ work be $M$ and $1$ woman's $1 \, \text{day}$ work be $W$.
Total work = $28 \times 15 \times M = 15 \times 24 \times W$.
$28 M = 24 W \implies \frac{M}{W} = \frac{24}{28} = \frac{6}{7}$.
Work done by $30$ men in $1 \, \text{day} = 30 M$.
Work done by $18$ women in $1 \, \text{day} = 18 W$.
Ratio = $\frac{30 M}{18 W} = \frac{30}{18} \times \frac{M}{W} = \frac{5}{3} \times \frac{6}{7} = \frac{5 \times 2}{7} = \frac{10}{7}$.
Thus,the ratio is $10:7$.
268
EasyMCQ
$20$ men can complete a piece of work in $16$ days. After $5$ days from the start of the work,some men left. If the remaining work was completed by the remaining men in $18 \frac{1}{3}$ days,how many men left after $5$ days from the start of the work?
A
$4$
B
$10$
C
$8$
D
$5$

Solution

(C) Total work = $20 \times 16 = 320$ man-days.
Work done in $5$ days = $20 \times 5 = 100$ man-days.
Remaining work = $320 - 100 = 220$ man-days.
Let $x$ be the number of men who left. The remaining men = $(20 - x)$.
The remaining work is completed in $18 \frac{1}{3} = \frac{55}{3}$ days.
Using the formula $\text{Work} = \text{Men} \times \text{Days}$:
$220 = (20 - x) \times \frac{55}{3}$.
$220 \times \frac{3}{55} = 20 - x$.
$4 \times 3 = 20 - x$.
$12 = 20 - x$.
$x = 20 - 12 = 8$.
Therefore,$8$ men left the work.
269
DifficultMCQ
$A$ and $B$ can do a piece of work in $30$ and $36$ days respectively. They began the work together,but $A$ leaves after some days and $B$ finished the remaining work in $25$ days. After how many days did $A$ leave?
A
$10$
B
$6$
C
$5$
D
$11$

Solution

(C) Efficiency of $A = 1/30$ units per day.
Efficiency of $B = 1/36$ units per day.
Let $A$ and $B$ work together for $x$ days.
Work done by $B$ alone in $25$ days $= 25 \times (1/36) = 25/36$.
Remaining work done by $A$ and $B$ together $= 1 - 25/36 = 11/36$.
Combined efficiency of $A$ and $B = 1/30 + 1/36 = (6+5)/180 = 11/180$.
Time taken by $A$ and $B$ to complete $11/36$ of the work $= (11/36) / (11/180) = (11/36) \times (180/11) = 5$ days.
Therefore,$A$ left the work after $5$ days.
270
MediumMCQ
$A,$ $B,$ and $C$ can do a work separately in $16,$ $32,$ and $48$ days respectively. They started the work together,but $B$ left $8$ days before and $C$ left $6$ days before the completion of the work. In what time is the work finished? (in days)
A
$9$
B
$12$
C
$14$
D
$10$

Solution

(B) Let the total time taken to complete the work be $x$ days.
Since $A$ worked for the entire duration,$B$ left $8$ days before completion,and $C$ left $6$ days before completion,their individual work contributions are:
Work done by $A = \frac{x}{16}$
Work done by $B = \frac{x-8}{32}$
Work done by $C = \frac{x-6}{48}$
The sum of their work equals $1$ (the whole work):
$\frac{x}{16} + \frac{x-8}{32} + \frac{x-6}{48} = 1$
Taking the least common multiple $(LCM)$ of $16, 32,$ and $48$,which is $96$:
$\frac{6x + 3(x-8) + 2(x-6)}{96} = 1$
$6x + 3x - 24 + 2x - 12 = 96$
$11x - 36 = 96$
$11x = 132$
$x = \frac{132}{11} = 12$ days.
Thus,the work is finished in $12$ days.
271
DifficultMCQ
$P$ and $Q$ together can do a job in $6$ days. $Q$ and $R$ can finish the same job in $60/7$ days. $P$ started the work and worked for $3$ days. $Q$ and $R$ continued for $6$ days. Then the difference of days in which $R$ and $P$ can complete the job is
A
$12$
B
$10$
C
$8$
D
$15$

Solution

(B) $(P+Q)$'s $1$ day work $= 1/6$.
$(Q+R)$'s $1$ day work $= 7/60$.
Let $P$ alone take $x$ days to finish the work.
According to the question,$P$ worked for $3$ days and $(Q+R)$ worked for $6$ days to complete the total work ($1$ unit).
So,$3/x + 6 \times (7/60) = 1$.
$3/x + 42/60 = 1$.
$3/x + 7/10 = 1$.
$3/x = 1 - 7/10 = 3/10$.
$x = 10$ days.
$Q$'s $1$ day work $= (P+Q) - P = 1/6 - 1/10 = (5-3)/30 = 2/30 = 1/15$.
$R$'s $1$ day work $= (Q+R) - Q = 7/60 - 1/15 = (7-4)/60 = 3/60 = 1/20$.
$R$ alone takes $20$ days to finish the work.
The difference in days taken by $R$ and $P$ is $20 - 10 = 10$ days.
272
DifficultMCQ
$A$ and $B$ can do a piece of work in $8$ days,$B$ and $C$ can do the same work in $12$ days,and $A, B,$ and $C$ together complete it in $6$ days. The number of days required to finish the work by $A$ and $C$ together is:
A
$16$
B
$12$
C
$8$
D
$24$

Solution

(C) Let the total work be the Least Common Multiple $(LCM)$ of $8, 12,$ and $6$,which is $24$ units.
Efficiency of $(A+B) = 24 / 8 = 3$ units/day.
Efficiency of $(B+C) = 24 / 12 = 2$ units/day.
Efficiency of $(A+B+C) = 24 / 6 = 4$ units/day.
To find the efficiency of $B$,we use the equation: $(A+B) + (B+C) - (A+B+C) = B$.
Efficiency of $B = 3 + 2 - 4 = 1$ unit/day.
Now,find the efficiency of $(A+C)$:
Efficiency of $(A+C) = (A+B+C) - B = 4 - 1 = 3$ units/day.
Time taken by $A$ and $C$ to complete the work = Total work / Efficiency of $(A+C) = 24 / 3 = 8$ days.
273
MediumMCQ
$A, B$ and $C$ can do a piece of work in $24, 30$ and $40$ days respectively. They began the work together,but $C$ left $4$ days before the completion of the work. In how many days was the work done?
A
$12$
B
$13$
C
$14$
D
$11$

Solution

(D) Efficiency of $A = \frac{1}{24}$ units/day.
Efficiency of $B = \frac{1}{30}$ units/day.
Efficiency of $C = \frac{1}{40}$ units/day.
Total work ($LCM$ of $24, 30, 40$) $= 120$ units.
Efficiency of $A = 5$ units/day,$B = 4$ units/day,$C = 3$ units/day.
Combined efficiency of $(A+B+C) = 5+4+3 = 12$ units/day.
Let the total time taken to complete the work be $x$ days.
$C$ left $4$ days before completion,so $C$ worked for $(x-4)$ days,while $A$ and $B$ worked for $x$ days.
Equation: $5x + 4x + 3(x-4) = 120$.
$9x + 3x - 12 = 120$.
$12x = 132$.
$x = 11$ days.
Thus,the total work was completed in $11$ days.
274
DifficultMCQ
$A$ can do a work in $10 \text{ days}$ and $B$ in $20 \text{ days}$. If they work together on it for $5 \text{ days}$,then the fraction of the work that is left is:
A
$\frac{4}{3}$
B
$\frac{1}{4}$
C
$\frac{3}{4}$
D
$\frac{3}{20}$

Solution

(B) Step $1$: Calculate the work done per day by $A$ and $B$.
$A$ completes the work in $10 \text{ days}$,so $A$'s $1 \text{ day}$ work $= \frac{1}{10}$.
$B$ completes the work in $20 \text{ days}$,so $B$'s $1 \text{ day}$ work $= \frac{1}{20}$.
Step $2$: Calculate the combined work done by $A$ and $B$ in $1 \text{ day}$.
$(A + B)$'s $1 \text{ day}$ work $= \frac{1}{10} + \frac{1}{20} = \frac{2+1}{20} = \frac{3}{20}$.
Step $3$: Calculate the work done by them in $5 \text{ days}$.
Work done in $5 \text{ days} = 5 \times \frac{3}{20} = \frac{15}{20} = \frac{3}{4}$.
Step $4$: Calculate the remaining work.
Remaining work $= 1 - \frac{3}{4} = \frac{1}{4}$.
275
DifficultMCQ
$A$ and $B$ together can do a piece of work in $30$ days. $B$ and $C$ together can do it in $20$ days. $A$ starts the work and works on it for $5$ days,then $B$ takes over and works for $15$ days. Finally,$C$ finishes the work in $18$ days. The number of days in which $C$ alone can do the work is (in days):
A
$24$
B
$40$
C
$60$
D
$120$

Solution

(A) Let the total work be the $LCM$ of $30$ and $20$,which is $60$ units.
Efficiency of $(A + B) = \frac{60}{30} = 2$ units/day.
Efficiency of $(B + C) = \frac{60}{20} = 3$ units/day.
Let $A, B, C$ be the efficiencies of $A, B, C$ respectively.
$A + B = 2$ $(i)$
$B + C = 3$ (ii)
Total work done = $5A + 15B + 18C = 60$.
We can rewrite this as $5(A + B) + 10B + 18C = 60$.
Substitute $(A + B) = 2$:
$5(2) + 10B + 18C = 60 \Rightarrow 10 + 10B + 18C = 60 \Rightarrow 10B + 18C = 50 \Rightarrow 5B + 9C = 25$ (iii).
From (ii),$B = 3 - C$. Substitute this into (iii):
$5(3 - C) + 9C = 25 \Rightarrow 15 - 5C + 9C = 25 \Rightarrow 4C = 10 \Rightarrow C = 2.5$ units/day.
Time taken by $C$ alone = $\frac{\text{Total Work}}{\text{Efficiency of } C} = \frac{60}{2.5} = 24$ days.
276
EasyMCQ
If $A, B,$ and $C$ can complete a work in $6$ days together. If $A$ can work twice as fast as $B$ and thrice as fast as $C$,then the number of days $C$ alone can complete the work is (in days):
A
$11$
B
$33$
C
$44$
D
$22$

Solution

(B) Let the efficiency of $C$ be $k$. Since $A$ is thrice as fast as $C$,the efficiency of $A$ is $3k$.
Since $A$ is twice as fast as $B$,the efficiency of $B$ is $\frac{3k}{2} = 1.5k$.
The total efficiency of $A, B,$ and $C$ is $3k + 1.5k + k = 5.5k$.
Given that they complete the work in $6$ days,the total work is $6 \times 5.5k = 33k$.
To find the time taken by $C$ alone,we divide the total work by the efficiency of $C$:
Time taken by $C = \frac{33k}{k} = 33$ days.
277
EasyMCQ
$A$'s $2$ days work is equal to $B$'s $3$ days work. If $A$ can complete the work in $8$ days,then to complete the work $B$ will take (in days):
A
$14$
B
$15$
C
$16$
D
$12$

Solution

(D) Given that $A$'s $2$ days work is equal to $B$'s $3$ days work.
Let the efficiency of $A$ be $E_A$ and $B$ be $E_B$.
So,$2 \times E_A = 3 \times E_B$.
This implies the ratio of their efficiencies is $\frac{E_A}{E_B} = \frac{3}{2}$.
Since time taken is inversely proportional to efficiency,the ratio of time taken by $A$ and $B$ to complete the same work is $\frac{T_A}{T_B} = \frac{E_B}{E_A} = \frac{2}{3}$.
Given that $A$ completes the work in $8$ days $(T_A = 8)$.
Substituting the values: $\frac{8}{T_B} = \frac{2}{3}$.
$2 \times T_B = 8 \times 3$.
$2 \times T_B = 24$.
$T_B = 12$ days.
Therefore,$B$ will take $12$ days to complete the work.
278
MediumMCQ
$4$ men and $6$ women complete a work in $8$ days,$2$ men and $9$ women also complete the same work in $8$ days. In how many days will $18$ women complete the work?
A
$4 \frac{2}{3}$
B
$5 \frac{2}{3}$
C
$4 \frac{1}{3}$
D
$5 \frac{1}{3}$

Solution

(D) Let $M$ be the work done by a man in one day and $W$ be the work done by a woman in one day.
According to the problem:
$(4M + 6W) \times 8 = (2M + 9W) \times 8$
Dividing both sides by $8$,we get:
$4M + 6W = 2M + 9W$
$2M = 3W$
This means $2$ men are equivalent to $3$ women.
Now,substitute $2M = 3W$ into the first case:
$4M + 6W = 2(2M) + 6W = 2(3W) + 6W = 6W + 6W = 12W$.
So,$12$ women can complete the work in $8$ days.
To find the time taken by $18$ women,we use the formula $W_1 \times D_1 = W_2 \times D_2$:
$12 \times 8 = 18 \times D_2$
$D_2 = \frac{12 \times 8}{18} = \frac{96}{18} = \frac{16}{3} = 5 \frac{1}{3}$ days.
279
MediumMCQ
If $4$ men or $8$ women can do a piece of work in $15$ days,in how many days can $6$ men and $12$ women do the same piece of work?
A
$5$
B
$20$
C
$15$
D
$10$

Solution

(A) Given that $4$ men can do the work in $15$ days,so $1$ man can do the work in $15 \times 4 = 60$ days.
Therefore,the work done by $1$ man in $1$ day is $\frac{1}{60}$.
Similarly,$8$ women can do the work in $15$ days,so $1$ woman can do the work in $15 \times 8 = 120$ days.
Therefore,the work done by $1$ woman in $1$ day is $\frac{1}{120}$.
Now,we need to find the work done by $6$ men and $12$ women in $1$ day:
Work done by $6$ men $= 6 \times \frac{1}{60} = \frac{1}{10}$.
Work done by $12$ women $= 12 \times \frac{1}{120} = \frac{1}{10}$.
Total work done by $6$ men and $12$ women in $1$ day $= \frac{1}{10} + \frac{1}{10} = \frac{2}{10} = \frac{1}{5}$.
Thus,the total time taken to complete the work is $5$ days.
280
EasyMCQ
$A, B$ and $C$ are employed to do a piece of work for $Rs. 575$. $A$ and $C$ are supposed to finish $\frac{19}{23}$ of the work together. The amount to be paid to $B$ is (in $Rs.$)
A
$210$
B
$100$
C
$200$
D
$475$

Solution

(B) The total work is considered as $1$ unit.
Given that $A$ and $C$ together finish $\frac{19}{23}$ of the work.
Therefore,the work done by $B$ is $1 - \frac{19}{23} = \frac{23 - 19}{23} = \frac{4}{23}$.
The wages are distributed in proportion to the work done.
Thus,the share of $B$ is $\frac{4}{23}$ of the total amount.
$B$'s share $= \frac{4}{23} \times 575 = 4 \times 25 = Rs. 100$.
281
EasyMCQ
$A$ man is twice as fast as a woman and a woman is twice as fast as a boy in doing a work. If all of them, a man, a woman and a boy, can finish the work in $7$ days, in how many days will a boy do it alone?
A
$49$
B
$7$
C
$6$
D
$42$

Solution

(A) Let the efficiency of a boy be $1$ unit/day.
Since a woman is twice as fast as a boy, the efficiency of a woman is $2$ units/day.
Since a man is twice as fast as a woman, the efficiency of a man is $2 \times 2 = 4$ units/day.
Total efficiency of a man, a woman, and a boy together $= 4 + 2 + 1 = 7$ units/day.
Total work $= \text{Total efficiency} \times \text{Total days} = 7 \text{ units/day} \times 7 \text{ days} = 49$ units.
Time taken by a boy to complete the work alone $= \frac{\text{Total work}}{\text{Efficiency of a boy}} = \frac{49}{1} = 49$ days.
282
EasyMCQ
$A, B$ and $C$ can do a job in $6$ days,$12$ days and $15$ days,respectively. After $\frac{1}{8}$ of the work is completed,$C$ leaves the job. The rest of the work is done by $A$ and $B$ together. The total time taken to finish the work is (in days):
A
$5 \frac{5}{6}$
B
$5 \frac{1}{4}$
C
$3 \frac{1}{2}$
D
$3 \frac{3}{4}$

Solution

(C) Step $1$: Calculate the work done by $C$ before leaving.
$C$ leaves after $\frac{1}{8}$ of the work is completed.
Step $2$: Calculate the remaining work.
Remaining work $= 1 - \frac{1}{8} = \frac{7}{8}$.
Step $3$: Calculate the combined efficiency of $A$ and $B$.
$A$'s $1$ day work $= \frac{1}{6}$.
$B$'s $1$ day work $= \frac{1}{12}$.
$(A + B)$'s $1$ day work $= \frac{1}{6} + \frac{1}{12} = \frac{2 + 1}{12} = \frac{3}{12} = \frac{1}{4}$.
Step $4$: Calculate the time taken by $A$ and $B$ to complete the remaining work.
Time $= \frac{\text{Remaining Work}}{\text{Combined Efficiency}} = \frac{7/8}{1/4} = \frac{7}{8} \times 4 = \frac{7}{2} = 3 \frac{1}{2}$ days.
283
MediumMCQ
$15$ men take $20$ days to complete a job working $8$ hours a day. The number of hours a day $20$ men should work to complete the same job in $12$ days is:
A
$5$
B
$10$
C
$15$
D
$18$

Solution

(B) We use the formula for work equivalence: $M_{1} \times D_{1} \times T_{1} = M_{2} \times D_{2} \times T_{2}$
Given:
$M_{1} = 15$ men,$D_{1} = 20$ days,$T_{1} = 8$ hours/day
$M_{2} = 20$ men,$D_{2} = 12$ days,$T_{2} = ?$
Substituting the values into the formula:
$15 \times 20 \times 8 = 20 \times 12 \times T_{2}$
Solving for $T_{2}$:
$T_{2} = \frac{15 \times 20 \times 8}{20 \times 12}$
$T_{2} = \frac{15 \times 8}{12}$
$T_{2} = \frac{120}{12} = 10$ hours/day.
284
EasyMCQ
Raj and Ram working together can do a piece of work in $10 \text{ days}$. Raj alone can do it in $12 \text{ days}$. In how many days will Ram alone do the work?
A
$20$
B
$40$
C
$50$
D
$60$

Solution

(D) The work done by $(Raj + Ram)$ in $1 \text{ day} = \frac{1}{10}$.
The work done by $Raj$ in $1 \text{ day} = \frac{1}{12}$.
Therefore,the work done by $Ram$ in $1 \text{ day} = \frac{1}{10} - \frac{1}{12}$.
Taking the least common multiple $(LCM)$ of $10$ and $12$,which is $60$:
$Ram$'s $1 \text{ day work} = \frac{6 - 5}{60} = \frac{1}{60}$.
Thus,$Ram$ alone will complete the work in $60 \text{ days}$.
285
MediumMCQ
$A,$ $B,$ and $C$ have to type $506$ pages to finish an assignment. $A$ can type a page in $12$ minutes,$B$ in $15$ minutes,and $C$ in $24$ minutes. If they divide the task into three parts so that all three of them spend an equal amount of time typing,what is the number of pages that $B$ should type?
A
$172$
B
$176$
C
$154$
D
$168$

Solution

(B) Let the time spent by each person be $T$ minutes.
The rate of typing for $A$ is $1/12$ pages per minute.
The rate of typing for $B$ is $1/15$ pages per minute.
The rate of typing for $C$ is $1/24$ pages per minute.
Since they spend equal time $T$,the number of pages typed by $A, B,$ and $C$ are $T/12, T/15,$ and $T/24$ respectively.
The total number of pages is $506$,so:
$T/12 + T/15 + T/24 = 506$
To solve for $T$,find the least common multiple of $12, 15,$ and $24$,which is $120$.
$(10T + 8T + 5T) / 120 = 506$
$23T / 120 = 506$
$T = (506 \times 120) / 23 = 22 \times 120 = 2640$ minutes.
The number of pages typed by $B$ is $T/15 = 2640 / 15 = 176$ pages.
286
EasyMCQ
$A$ can complete a work in $m$ days and $B$ can complete it in $n$ days. How many days will it take to complete the work if both $A$ and $B$ work together?
A
$(m+n)$
B
$(\frac{1}{m} \times \frac{1}{n})$
C
$(\frac{m+n}{mn})$
D
$(\frac{mn}{m+n})$

Solution

(D) Work done by $A$ in $1$ day $= \frac{1}{m}$.
Work done by $B$ in $1$ day $= \frac{1}{n}$.
Work done by both $A$ and $B$ together in $1$ day $= \frac{1}{m} + \frac{1}{n} = \frac{n+m}{mn}$.
Therefore,the total time taken by $A$ and $B$ to complete the work together is the reciprocal of the work done in $1$ day.
Time taken $= \frac{mn}{m+n}$ days.
287
MediumMCQ
Three men $A, B, C$ working together can do a job in $6$ hours less time than $A$ alone,in $1$ hour less time than $B$ alone,and in one-half the time needed by $C$ when working alone. Then $A$ and $B$ together can do the job in (in hours):
A
$2/3$
B
$3/4$
C
$3/2$
D
$4/3$

Solution

(D) Let the time taken by $A, B, C$ working together be $t$ hours.
Then $A$ takes $(t+6)$ hours,$B$ takes $(t+1)$ hours,and $C$ takes $2t$ hours.
The combined work rate is $\frac{1}{t+6} + \frac{1}{t+1} + \frac{1}{2t} = \frac{1}{t}$.
Subtracting $\frac{1}{2t}$ from both sides: $\frac{1}{t+6} + \frac{1}{t+1} = \frac{1}{2t}$.
$\frac{(t+1) + (t+6)}{(t+6)(t+1)} = \frac{1}{2t} \Rightarrow \frac{2t+7}{t^2+7t+6} = \frac{1}{2t}$.
$4t^2 + 14t = t^2 + 7t + 6 \Rightarrow 3t^2 + 7t - 6 = 0$.
$(3t-2)(t+3) = 0$. Since time must be positive,$t = 2/3$ hours.
Now,$A$ takes $2/3 + 6 = 20/3$ hours and $B$ takes $2/3 + 1 = 5/3$ hours.
Combined rate of $A$ and $B = \frac{3}{20} + \frac{3}{5} = \frac{3+12}{20} = \frac{15}{20} = 3/4$ work per hour.
Time taken by $A$ and $B$ together = $4/3$ hours.
288
MediumMCQ
$A$ takes three times as long as $B$ and $C$ together to do a job. $B$ takes four times as long as $A$ and $C$ together to do the work. If all the three,working together,can complete the job in $24$ days,then the number of days $A$ alone will take to finish the job is:
A
$100$
B
$96$
C
$95$
D
$90$

Solution

(B) Let the time taken by $(B+C)$ be $x$ days. Then,the time taken by $A$ is $3x$ days.
Therefore,the work done by $(A+B+C)$ in $1$ day is $\frac{1}{3x} + \frac{1}{x} = \frac{1+3}{3x} = \frac{4}{3x}$.
Given that $(A+B+C)$ complete the work in $24$ days,so $\frac{4}{3x} = \frac{1}{24}$.
$3x = 4 \times 24 = 96$,so $x = 32$ days.
Thus,$A$ takes $3x = 3 \times 32 = 96$ days to finish the job alone.
289
MediumMCQ
$P$ can do a piece of work in $9$ days. $Q$ is $50\%$ more efficient than $P$. The number of days it takes for $Q$ to do the same piece of work is
A
$6$
B
$3$
C
$13\frac{1}{2}$
D
$4\frac{1}{2}$

Solution

(A) The efficiency of $P$ is taken as $100\%$. Since $Q$ is $50\%$ more efficient than $P$,the efficiency of $Q$ is $150\%$.
The ratio of efficiency of $Q$ to $P$ is $150 : 100$,which simplifies to $3 : 2$.
Since time taken is inversely proportional to efficiency,the ratio of time taken by $Q$ to $P$ is $2 : 3$.
Given that $P$ takes $9$ days,which corresponds to $3$ parts in the ratio.
Therefore,$1$ part corresponds to $\frac{9}{3} = 3$ days.
Since $Q$ takes $2$ parts,the time taken by $Q$ is $2 \times 3 = 6$ days.
290
DifficultMCQ
Sixteen men can complete a work in $15$ days,$24$ children can do the same work in $20$ days. In how many days will $8$ men and $8$ children complete the same work?
A
$20$
B
$18$
C
$16$
D
$13\frac{1}{3}$

Solution

(A) Given that $16$ men can complete the work in $15$ days.
Therefore,$8$ men can complete the same work in $16 \times 15 / 8 = 30$ days.
Given that $24$ children can complete the work in $20$ days.
Therefore,$8$ children can complete the same work in $24 \times 20 / 8 = 60$ days.
Let the total work be the $LCM$ of $30$ and $60$,which is $60$ units.
Efficiency of $8$ men per day $= 60 / 30 = 2$ units/day.
Efficiency of $8$ children per day $= 60 / 60 = 1$ unit/day.
Combined efficiency of $8$ men and $8$ children $= 2 + 1 = 3$ units/day.
Time taken to complete the work $= 60 / 3 = 20$ days.
291
MediumMCQ
$A$ can do a piece of work in $4 \, days$ and $B$ can do it in $12 \, days.$ In how many $days$ will they finish the work,both working together?
A
$2$
B
$3$
C
$4$
D
$6$

Solution

(B) Given that $A$ completes the work in $4 \, days$ and $B$ completes it in $12 \, days$.
Total work is taken as the $LCM$ of $4$ and $12$,which is $12 \, units$.
Efficiency of $A = \frac{12 \, units}{4 \, days} = 3 \, units/day$.
Efficiency of $B = \frac{12 \, units}{12 \, days} = 1 \, unit/day$.
Combined efficiency of $A$ and $B = 3 + 1 = 4 \, units/day$.
Time taken by both working together $= \frac{\text{Total work}}{\text{Combined efficiency}} = \frac{12}{4} = 3 \, days$.
292
MediumMCQ
$A$ can do $\frac{1}{4}$ of a work in $10$ days. $B$ can do $\frac{1}{3}$ of the work in $20$ days. In how many days can both $A$ and $B$ together do the work?
A
$24$
B
$25$
C
$30$
D
$32$

Solution

(A) If $A$ can do $\frac{1}{4}$ of the work in $10$ days,then $A$ can complete the whole work in $10 \times 4 = 40$ days.
If $B$ can do $\frac{1}{3}$ of the work in $20$ days,then $B$ can complete the whole work in $20 \times 3 = 60$ days.
Let the total work be the Least Common Multiple $(LCM)$ of $40$ and $60$,which is $120$ units.
Efficiency of $A = \frac{120}{40} = 3$ units/day.
Efficiency of $B = \frac{120}{60} = 2$ units/day.
Combined efficiency of $A$ and $B = 3 + 2 = 5$ units/day.
Time taken by $A$ and $B$ together to complete the work $= \frac{\text{Total work}}{\text{Combined efficiency}} = \frac{120}{5} = 24$ days.
293
EasyMCQ
$A$ and $B$ can together finish a work in $30$ days. They worked at it for $20$ days and then $B$ left. The remaining work was done by $A$ alone in $20$ more days. $A$ alone can finish the work in (in days):
A
$48$
B
$50$
C
$60$
D
$54$

Solution

(C) Let the total work be $W = 1$ unit.
Combined efficiency of $A$ and $B$ is $(A+B) = \frac{1}{30}$ units/day.
Work done by $A$ and $B$ in $20$ days $= 20 \times \frac{1}{30} = \frac{2}{3}$ units.
Remaining work $= 1 - \frac{2}{3} = \frac{1}{3}$ units.
$A$ completes this $\frac{1}{3}$ units of work in $20$ days.
Therefore,efficiency of $A = \frac{1/3}{20} = \frac{1}{60}$ units/day.
Time taken by $A$ alone to finish the total work $= \frac{1}{1/60} = 60$ days.
294
EasyMCQ
If $x$ men can do a piece of work in $x$ days,then the number of days in which $y$ men can do the same work is (in days)
A
$x y$
B
$\frac{y^{2}}{x}$
C
$\frac{x^{2}}{y}$
D
$x^{2} y$

Solution

(C) According to the formula for work,$M_{1} \times D_{1} = M_{2} \times D_{2}$,where $M$ is the number of men and $D$ is the number of days.
Given: $M_{1} = x$,$D_{1} = x$,$M_{2} = y$,and we need to find $D_{2}$.
Substituting the values: $x \times x = y \times D_{2}$.
Therefore,$D_{2} = \frac{x^{2}}{y}$ days.
295
MediumMCQ
$3$ persons undertake to complete a piece of work for $Rs. 1,200$. The $first$ person can complete the work in $8$ days,the $second$ person in $12$ days,and the $third$ person in $16$ days. They complete the work with the help of a $fourth$ person in $3$ days. What does the $fourth$ person get? (in $Rs.$)
A
$180$
B
$200$
C
$225$
D
$250$

Solution

(C) Let the work done by the $first$,$second$,$third$,and $fourth$ person in $1$ day be $W_1, W_2, W_3$,and $W_4$ respectively.
$W_1 = 1/8$,$W_2 = 1/12$,$W_3 = 1/16$.
Let the $fourth$ person complete the work in $x$ days,so $W_4 = 1/x$.
Since they complete the work together in $3$ days:
$3(1/8 + 1/12 + 1/16 + 1/x) = 1$
$1/8 + 1/12 + 1/16 + 1/x = 1/3$
$1/x = 1/3 - (6+4+3)/48 = 1/3 - 13/48 = (16-13)/48 = 3/48 = 1/16$.
Thus,the $fourth$ person's work share in $3$ days is $3 \times (1/16) = 3/16$.
The wages are distributed in proportion to the work done by each person.
$Fourth$ person's share $= (3/16) \times 1200 = 3 \times 75 = 225$ $Rs.$
296
MediumMCQ
Two workers $A$ and $B$ working together completed a job in $5$ days. If $A$ worked twice as efficiently as he actually did and $B$ worked $1/3$ as efficiently as he actually did,the work would have been completed in $3$ days. To complete the job alone,$A$ would require (in days):
A
$5 \frac{1}{5}$
B
$6 \frac{1}{4}$
C
$7 \frac{1}{2}$
D
$8 \frac{3}{4}$

Solution

(B) Let $A$ alone do the work in $x$ days and $B$ alone do the work in $y$ days.
According to the problem,the work done by $A$ and $B$ in one day is $1/x$ and $1/y$ respectively.
Given that $A$ and $B$ together complete the job in $5$ days,we have: $1/x + 1/y = 1/5$ .....$(1)$
If $A$ works with double efficiency $(2/x)$ and $B$ works with $1/3$ efficiency $(1/(3y))$,they complete the job in $3$ days: $2/x + 1/(3y) = 1/3$ .....$(2)$
To solve for $x$,multiply equation $(2)$ by $3$: $6/x + 1/y = 1$ .....$(3)$
Subtract equation $(1)$ from equation $(3)$: $(6/x + 1/y) - (1/x + 1/y) = 1 - 1/5$
$5/x = 4/5$
$x = 25/4 = 6 \frac{1}{4}$ days.
Thus,$A$ alone would require $6 \frac{1}{4}$ days to complete the job.
297
MediumMCQ
$A$ can do a piece of work in $20$ days and $B$ in $30$ days. They work together for $7$ days and then both leave the work. Then $C$ alone finishes the remaining work in $10$ days. In how many days will $C$ finish the full work?
A
$25$
B
$30$
C
$24$
D
$20$

Solution

(C) Work done by $A$ in one day $= \frac{1}{20}$.
Work done by $B$ in one day $= \frac{1}{30}$.
Combined work of $A$ and $B$ in one day $= \frac{1}{20} + \frac{1}{30} = \frac{3+2}{60} = \frac{5}{60} = \frac{1}{12}$.
Work done by $A$ and $B$ in $7$ days $= 7 \times \frac{1}{12} = \frac{7}{12}$.
Remaining work $= 1 - \frac{7}{12} = \frac{5}{12}$.
$C$ finishes the remaining $\frac{5}{12}$ work in $10$ days.
Therefore,$C$ will finish the full work in $10 \times \frac{12}{5} = 24$ days.
298
MediumMCQ
Sunil completes a work in $4$ days,whereas Dinesh completes the work in $6$ days. Ramesh works $1 \frac{1}{2}$ times as fast as Sunil. The three together can complete the work in (in days):
A
$1 \frac{5}{12}$
B
$1 \frac{5}{7}$
C
$1 \frac{3}{8}$
D
$1 \frac{5}{19}$

Solution

(D) Sunil's $1$ day work $= \frac{1}{4}$.
Dinesh's $1$ day work $= \frac{1}{6}$.
Ramesh is $1 \frac{1}{2} = \frac{3}{2}$ times as fast as Sunil.
Therefore,Ramesh's $1$ day work $= \frac{3}{2} \times \frac{1}{4} = \frac{3}{8}$.
Work done by all three together in $1$ day $= \frac{1}{4} + \frac{1}{6} + \frac{3}{8}$.
Taking the least common multiple $(LCM)$ of $4, 6, 8$ as $24$:
$= \frac{6 + 4 + 9}{24} = \frac{19}{24}$.
Time taken by all three to complete the work $= \frac{24}{19} = 1 \frac{5}{19}$ days.
299
EasyMCQ
$A$ farmer can plough a field working $6$ hours per day in $18$ days. How many hours per day must the farmer work to finish the same work in $12$ days?
A
$7$
B
$9$
C
$11$
D
$13$

Solution

(B) The total work done is constant. Let $D_1$ and $T_1$ be the days and hours per day for the first scenario,and $D_2$ and $T_2$ be the days and hours per day for the second scenario.
The formula for total work is $D_1 \times T_1 = D_2 \times T_2$.
Given:
$D_1 = 18$ days
$T_1 = 6$ hours/day
$D_2 = 12$ days
Substituting the values:
$18 \times 6 = 12 \times T_2$
$108 = 12 \times T_2$
$T_2 = \frac{108}{12} = 9$ hours/day.
Therefore,the farmer must work $9$ hours per day.
300
EasyMCQ
Two men can do a piece of work in $x$ days. But $y$ women can do it in $3$ days. Then the ratio of the work done by $1$ man and $1$ woman is
A
$3y:2x$
B
$2x:3y$
C
$x:y$
D
$2y:3x$

Solution

(A) The work done by $2$ men in $x$ days is $1$ unit of work.
Therefore,the work done by $1$ man in $1$ day is $\frac{1}{2x}$.
The work done by $y$ women in $3$ days is $1$ unit of work.
Therefore,the work done by $1$ woman in $1$ day is $\frac{1}{3y}$.
The ratio of the work done by $1$ man to that of $1$ woman is $\frac{1}{2x} : \frac{1}{3y}$.
Multiplying both sides by $6xy$,we get $3y : 2x$.

Time and Work and Wages — Time and Work · Frequently Asked Questions

1Are these Time and Work and Wages questions useful for JEE and NEET?

Yes. All questions in this section are mapped to JEE Main and NEET exam patterns. Previous year questions from JEE Main, NEET, GUJCET and state-level exams are included with full solutions.

2Can I switch to Hindi or Gujarati for these questions?

Yes. Use the language tabs in the hero section or the sidebar to view the same questions and solutions in English, Hindi or Gujarati.

3How do I generate a question paper from this subtopic?

Use the Vedclass Exam Paper Generator — select the chapter and subtopic, set difficulty, and generate Sets A, B, C, D automatically. First 3 chapters of every subject are free.

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D papers from this chapter in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo
For Teachers & Institutes

Generate a Time and Work and Wages Exam Paper in 2 Minutes

Select subtopic & difficulty — Sets A, B, C, D auto-generated with No Repeat logic.

First 3 chapters of every subject are free — no payment required.