$A$ can do a piece of work in $4 \, days$ and $B$ can do it in $12 \, days.$ In how many $days$ will they finish the work,both working together?

  • A
    $2$
  • B
    $3$
  • C
    $4$
  • D
    $6$

Explore More

Similar Questions

$A$ is $30\%$ more efficient than $B.$ How much time will they,working together,take to complete a job which $A$ alone could have done in $23$ days? (in days)

Difficult
View Solution

$A$ contract is to be completed in $92$ days and $234$ men were set to work,each working $16$ hours a day. After $66$ days,$\frac{4}{7}$ of the work is completed. How many additional men may be employed,so that the work may be completed in time,each man now working $18$ hours a day?

Difficult
View Solution

Amit and Sujit together can complete a data entry assignment in $5$ days. Sujit's speed is $80\%$ of Amit's speed and the total key depressions in the assignment are $5,76,000$. What is Amit's speed in key depressions per hour if they work for $8$ hours a day?

$A$ and $B$ can complete a piece of work in $8$ days,$B$ and $C$ can do it in $12$ days,and $C$ and $A$ can do it in $8$ days. In how many days can $A, B,$ and $C$ together complete the work?

Bansal,Gupta,and Singhal together can complete a work in $4 \, \text{days}$. If Bansal and Gupta together can complete the work in $4 \frac{4}{5} \, \text{days}$,and Gupta and Singhal together can do it in $8 \, \text{days}$,then Gupta alone can complete the work in (in $\text{days}$):

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo