$15$ men take $20$ days to complete a job working $8$ hours a day. The number of hours a day $20$ men should work to complete the same job in $12$ days is:

  • A
    $5$
  • B
    $10$
  • C
    $15$
  • D
    $18$

Explore More

Similar Questions

$A$ and $B$ together can do a piece of work in $9$ days. If $A$ does thrice the work of $B$ in a given time,the time $A$ alone will take to finish the work is (in days)

$15$ men take $20$ days to complete a job working $8$ hours a day. How many hours a day should $20$ men work to complete the same job in $12$ days?

If $3$ men or $5$ women can reap a field in $43$ days,how long will $5$ men and $6$ women take to reap it? (in days)

$39$ persons can repair a road in $12$ days working $5$ hours per day. In how many days will $30$ persons working $6$ hours per day complete the same work?

$A$ can do a piece of work in $4\, h$,$B$ and $C$ can do it in $3\, h$,and $A$ and $C$ can do it in $2\, h$. How long will $B$ alone take to do it? (in $h$)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo