$A$ and $B$ can together finish a work in $30$ days. They worked at it for $20$ days and then $B$ left. The remaining work was done by $A$ alone in $20$ more days. $A$ alone can finish the work in (in days):

  • A
    $48$
  • B
    $50$
  • C
    $60$
  • D
    $54$

Explore More

Similar Questions

$4$ men and $6$ women together can complete a work in $8$ days,while $3$ men and $7$ women together can complete it in $10$ days. How many days will $20$ women working together take to complete the same work?

$A, B$ and $C$ individually can do a work in $10\, days, 12\, days$ and $15\, days,$ respectively. The number of days required to finish the work by $A, B$ and $C$ working together is? (in $days$)

$A$ and $B$ together can complete a work in $10$ days. They started together,but $A$ left after $2$ days and the remaining work was completed by $B$ in $12$ days. In how many days can $A$ complete the entire work while working alone?

Difficult
View Solution

$45$ men can complete a work in $16$ days. Four days after they started working,$36$ more men joined them. How many days will they now take to complete the remaining work?

Difficult
View Solution

Bansal,Gupta,and Singhal together can complete a work in $4 \, \text{days}$. If Bansal and Gupta together can complete the work in $4 \frac{4}{5} \, \text{days}$,and Gupta and Singhal together can do it in $8 \, \text{days}$,then Gupta alone can complete the work in (in $\text{days}$):

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo