$A, B$ and $C$ can do a job in $6$ days,$12$ days and $15$ days,respectively. After $\frac{1}{8}$ of the work is completed,$C$ leaves the job. The rest of the work is done by $A$ and $B$ together. The total time taken to finish the work is (in days):

  • A
    $5 \frac{5}{6}$
  • B
    $5 \frac{1}{4}$
  • C
    $3 \frac{1}{2}$
  • D
    $3 \frac{3}{4}$

Explore More

Similar Questions

$P, Q$ and $R$ can do a piece of work in $60$ days,$100$ days and $80$ days respectively. They work together to finish the work and receive $Rs. 2256$. Then $P$ will get (in $Rs.$)

Difficult
View Solution

$A$ track of $100\, m$ can be built by $7\, men$ or $10\, women$ in $70\, days.$ How many days will $14\, men$ and $20\, women$ take to build a track of $600\, m$?

Difficult
View Solution

$A$ and $B$ can do a work in $12$ days,$B$ and $C$ in $15$ days,and $C$ and $A$ in $20$ days. If $A, B,$ and $C$ work together,they will complete the work in (in days):

$4$ men or $6$ women or $10$ children can paint a house in $5$ days. The painting is given to a couple (a man and a woman) and their $5$ sons. They finish the job in (in days):

If $6$ men and $8$ boys can do a piece of work in $10$ days and $26$ men and $48$ boys can do the same work in $2$ days,the time taken by $15$ men and $20$ boys to do the same type of work will be (in days)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo