$39$ persons can repair a road in $12$ days working $5$ hours per day. In how many days will $30$ persons working $6$ hours per day complete the same work?

  • A
    $10$
  • B
    $13$
  • C
    $14$
  • D
    $15$

Explore More

Similar Questions

$A, B$ and $C$ completed a work costing $Rs. 1800$. $A$ worked for $6$ days,$B$ for $4$ days and $C$ for $9$ days. If their daily wages are in the ratio of $5: 6: 4$,how much amount will be received by $A$ (in $Rs.$)?

$A$ group of men decided to do a work in $10 \, days,$ but five of them absented themselves. If the rest of the group finished the work in $12 \, days,$ find the original number of men? (in $men$)

$A$ can do a piece of work in $14$ days,which $B$ can do in $21$ days. They begin together,but $3$ days before the completion of the work,$A$ leaves. The total number of days to complete the work is:

Difficult
View Solution

$2$ men and $1$ woman can do a piece of work in $14$ days,while $4$ women and $2$ men can do the same work in $8$ days. If a man gets $Rs. 90$ per day,what should be the wages per day of a woman? (in $Rs.$)

Difficult
View Solution

Shashi can do a piece of work in $20$ days. Tanya is $25\%$ more efficient than Shashi. The number of days taken by Tanya to do the same piece of work is

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo