If $3$ men or $5$ women can reap a field in $43$ days,how long will $5$ men and $6$ women take to reap it? (in days)

  • A
    $10$
  • B
    $12$
  • C
    $15$
  • D
    $18$

Explore More

Similar Questions

$A$ contractor has the target of completing a work in $40 \text{ days}$. He employed $20$ persons who completed $\frac{1}{4}$ of the work in $10 \text{ days}$ and left. The number of additional persons he has to employ to finish the remaining part of the work as per the target is:

$4$ men and $6$ women together can complete a work in $8$ days,while $3$ men and $7$ women together can complete it in $10$ days. $20$ women working together will complete it in (in days):

If $5$ men and $3$ boys can reap $23 \text{ hectares}$ in $4 \text{ days}$ and if $3$ men and $2$ boys can reap $7 \text{ hectares}$ in $2 \text{ days}$,how many boys must assist $7$ men in order that they may reap $45 \text{ hectares}$ in $6 \text{ days}$?

Difficult
View Solution

$A$ can do a work in $6$ days and $B$ can do the same work in $5$ days. The contract for the work is of $Rs. 220$. How much shall $B$ get if both of them work together? (in $Rs.$)

$15$ men take $20$ days to complete a job working $8$ hours a day. The number of hours a day $20$ men should work to complete the same job in $12$ days is:

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo