$A$ contractor has the target of completing a work in $40 \text{ days}$. He employed $20$ persons who completed $\frac{1}{4}$ of the work in $10 \text{ days}$ and left. The number of additional persons he has to employ to finish the remaining part of the work as per the target is:

  • A
    $10$
  • B
    $20$
  • C
    $40$
  • D
    $30$

Explore More

Similar Questions

$A$ takes three times as long as $B$ and $C$ together to do a job. $B$ takes four times as long as $A$ and $C$ together to do the work. If all the three,working together,can complete the job in $24$ days,then the number of days $A$ alone will take to finish the job is:

$A$ and $B$ can do a work in $12$ days. $B$ and $C$ can do the same work in $15$ days. $C$ and $A$ can do the same work in $20$ days. How much time will $A, B,$ and $C$ take to complete the same work together (in days)?

Difficult
View Solution

$A$ and $B$ can do a piece of work in $30$ and $36$ days respectively. They began the work together,but $A$ leaves after some days and $B$ finished the remaining work in $25$ days. After how many days did $A$ leave?

Difficult
View Solution

$A$ and $B$ together can do a piece of work in $30$ days. $A$ having worked for $16$ days,$B$ finishes the remaining work alone in $44$ days. In how many days shall $B$ finish the whole work alone?

$A$ can do a piece of work in $16$ days and $B$ in $24$ days. They take the help of $C$ and all three together finish the work in $6$ days. If the total remuneration for the work is $Rs. 400$,what is the amount (in $Rs.$) each will receive in proportion to the work done?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo