$A$ can do a work in $15 \text{ days}$ and $B$ in $20 \text{ days}$. If they work together on it for $4 \text{ days}$,then the fraction of the work that is left is

  • A
    $8/15$
  • B
    $7/15$
  • C
    $1/4$
  • D
    $1/10$

Explore More

Similar Questions

$A$ and $B$ can complete a piece of work in $12$ and $18 \text{ days}$ respectively. $A$ begins to do the work and they work alternatively one at a time for $1 \text{ day}$ each. The whole work will be completed in (in $\text{days}$):

$A$ can do $\frac{1}{3}$ of a work in $5 \text{ days}$ and $B$ can do $\frac{2}{5}$ of the work in $10 \text{ days}$. In how many $\text{days}$ can both $A$ and $B$ together do the work?

$A$ track of $100\, m$ can be built by $7\, men$ or $10\, women$ in $70\, days.$ How many days will $14\, men$ and $20\, women$ take to build a track of $600\, m$?

Difficult
View Solution

$A$ and $B$ can complete a piece of work in $18$ days; $B$ and $C$ in $24$ days; $C$ and $A$ in $36$ days. $A$ alone can complete the work in (in days):

$P, Q$ and $R$ undertake to do a work for $Rs. 707$. $P$ and $Q$ together do $\frac{5}{7}$ of the work and the rest is done by $R$ alone. How much should $R$ get? (in $Rs.$)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo