$A$ can complete a work in $10$ days,$B$ in $12$ days,and $C$ in $15$ days. All of them began the work together; but $A$ had to leave the work after $2$ days of the start and $B$ also left $3$ days before the completion of the work. How long did the work last? (in days)

  • A
    $7$
  • B
    $8$
  • C
    $10$
  • D
    $12$

Explore More

Similar Questions

$A$ can do a piece of work in $12$ days and $B$ in $15$ days. They work together for $5$ days and then $B$ leaves. The number of days taken by $A$ to finish the remaining work is:

$5$ men can prepare $10$ toys in $6$ days working $6$ hours a day. Then,in how many days can $12$ men prepare $16$ toys working $8$ hours a day? (in days)

$A$ can do a piece of work in $4\, h$,$B$ and $C$ can do it in $3\, h$,and $A$ and $C$ can do it in $2\, h$. How long will $B$ alone take to do it? (in $h$)

$10$ men can cut $15$ trees in $2$ hours. If $2$ men leave the job,how many trees will be cut in $3$ hours?

$15$ men take $20$ days to complete a job working $8$ hours a day. The number of hours a day $20$ men should work to complete the same job in $12$ days is:

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo