$A$ team of $30$ men is supposed to do a work in $38$ days. After $25$ days,$5$ more men were employed and the work was finished one day earlier. How many days would it have been delayed if $5$ more men were not employed? (in days)

  • A
    $1$
  • B
    $2$
  • C
    $3$
  • D
    $4$

Explore More

Similar Questions

$A$ man,a woman,and a boy can together complete a piece of work in $3$ days. If a man alone can do it in $6$ days and a boy alone in $18$ days,how long will a woman alone take to complete the work? (in days)

$A$ takes three times as long as $B$ and $C$ together to do a job. $B$ takes four times as long as $A$ and $C$ together to do the work. If all the three,working together,can complete the job in $24$ days,then the number of days $A$ alone will take to finish the job is:

$A$ and $B$ can do a piece of work in $12$ days, $B$ and $C$ in $8$ days, and $C$ and $A$ in $6$ days. How long would $B$ take to do the same work alone? (in days)

Difficult
View Solution

$28$ men can complete a piece of work in $15 \, \text{days}$ and $15$ women can complete the same piece of work in $24 \, \text{days}$. What is the respective ratio between the amount of work done by $30$ men in $1 \, \text{day}$ and the amount of work done by $18$ women in $1 \, \text{day}$?

$5$ men can prepare $10$ toys in $6$ days working $6$ hours a day. Then,in how many days can $12$ men prepare $16$ toys working $8$ hours a day? (in days)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo