$A$ contract on a construction job specifies a penalty for delay of completion beyond a certain date as follows: ₹ $200$ for the first day,₹ $250$ for the second day,₹ $300$ for the third day,etc. The penalty for each succeeding day is ₹ $50$ more than for the preceding day. How much money does the contractor have to pay as a penalty if he has delayed the work by $30$ days?

  • A
    $27743$
  • B
    $27891$
  • C
    $27653$
  • D
    $27750$

Explore More

Similar Questions

Write the first four terms of the $AP,$ when the first term $a$ and the common difference $d$ are given as follows: $a = -1, d = \frac{1}{2}$

Difficult
View Solution

Subba Rao started work in $1995$ at an annual salary of ₹ $5000$ and received an increment of ₹ $200$ each year. In which year did his income reach ₹ $7000$?

Difficult
View Solution

$2, \frac{5}{2}, 3, \frac{7}{2}, \ldots$ are $APs$? If they form an $AP$,find the common difference $d$ and write three more terms.

Difficult
View Solution

$A$ sum of ₹ $700$ is to be used to give seven cash prizes to students of a school for their overall academic performance. If each prize is ₹ $20$ less than its preceding prize,find the value of each of the prizes.

Difficult
View Solution

Are $\sqrt{3}, \sqrt{6}, \sqrt{9}, \sqrt{12}, \ldots$ in an $AP$? If they form an $AP$,find the common difference $d$ and write three more terms.

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo