$A$ can complete a piece of work in $12$ days. $B$ is $60\%$ more efficient than $A$. The number of days that $B$ will take to complete the same work is:

  • A
    $6$
  • B
    $7\frac{1}{2}$
  • C
    $8$
  • D
    $8\frac{1}{2}$

Explore More

Similar Questions

$P$ can complete $\frac{1}{4}$ of a work in $10$ days,$Q$ can complete $40\%$ of the same work in $15$ days,$R$ can complete $\frac{1}{3}$ of the work in $13$ days,and $S$ can complete $\frac{1}{6}$ of the work in $7$ days. Who will be able to complete the work first?

$3$ women and $18$ children together take $2$ days to complete a piece of work. How many days will $9$ children alone take to complete the piece of work,if $6$ women alone can complete the piece of work in $3$ days?

$P$ and $Q$ together can do a job in $6$ days. $Q$ and $R$ can finish the same job in $60/7$ days. $P$ started the work and worked for $3$ days. $Q$ and $R$ continued for $6$ days. Then the difference of days in which $R$ and $P$ can complete the job is

Difficult
View Solution

Sita takes twice as much time as Gita to complete a work and Rita does it in the same time as Sita and Gita together. If all three working together can finish the work in $6$ days,then the time taken by each of them to finish the work is (in days):

Difficult
View Solution

$A$ carpenter can build a cupboard in $48 \, \text{hours}$. After $12 \, \text{hours}$, he takes a break. What fraction of the cupboard is yet to be built?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo