$A$ and $B$ can do a work in $12$ days,$B$ and $C$ in $15$ days,and $C$ and $A$ in $20$ days. If $A, B,$ and $C$ work together,they will complete the work in (in days):

  • A
    $5$
  • B
    $7\frac{5}{6}$
  • C
    $10$
  • D
    $15\frac{2}{3}$

Explore More

Similar Questions

Two workers $A$ and $B$ working together completed a job in $5$ days. If $A$ worked twice as efficiently as he actually did and $B$ worked $1/3$ as efficiently as he actually did,the work would have been completed in $3$ days. To complete the job alone,$A$ would require (in days):

$A$ man,a woman,and a boy can together complete a piece of work in $3$ days. If a man alone can do it in $6$ days and a boy alone in $18$ days,how long will a woman alone take to complete the work? (in days)

$P$,$Q$ and $R$ contracted to do a work for $Rs. 4200$. $P$ can do the work in $6$ days,$Q$ in $10$ days and $R$ in $12$ days. If they work together to do the work,what is the share of $R$ (in $Rs.$)?

$A$ is twice as good a workman as $B$. Working together,they finish a piece of work in $1.5$ days. $A$ alone can finish the work in (in days):

$A, B$ and $C$ can do a piece of work in $16, 32$ and $48$ days,respectively. They started working together,but $C$ left after working $4$ days and $B$ left $2$ days before the completion of the work. The total number of days taken for the completion of the work was (in days):

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo