$A, B$ and $C$ can complete a piece of work in $6, 12$ and $24$ days respectively. They altogether will complete the work in (in days):

  • A
    $5 \frac{2}{7}$
  • B
    $4 \frac{3}{7}$
  • C
    $3 \frac{3}{7}$
  • D
    none of these

Explore More

Similar Questions

Sixteen men can complete a work in $15$ days,$24$ children can do the same work in $20$ days. In how many days will $8$ men and $8$ children complete the same work?

Difficult
View Solution

If $8$ men or $10$ women can do a piece of work in $50$ days,in what time will $28$ men and $15$ women do it? (in days)

Difficult
View Solution

$4$ men and $6$ women together can complete a work in $8$ days,while $3$ men and $7$ women together can complete it in $10$ days. $20$ women working together will complete it in (in days):

If $5$ men and $3$ boys can reap $23 \text{ hectares}$ in $4 \text{ days}$ and if $3$ men and $2$ boys can reap $7 \text{ hectares}$ in $2 \text{ days}$,how many boys must assist $7$ men in order that they may reap $45 \text{ hectares}$ in $6 \text{ days}$?

Difficult
View Solution

$A, B$ and $C$ can do a piece of work individually in $8, 10$ and $15$ days respectively. $A$ and $B$ start working,but $A$ quits after working for $2$ days. After this,$C$ joins $B$ until the completion of the work. In how many days will the work be completed?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo