$A, B$ and $C$ together can finish a piece of work in $4$ days. $A$ alone can do it in $12$ days and $B$ alone in $18$ days. How many days will be taken by $C$ to do it alone?

  • A
    $21$
  • B
    $16$
  • C
    $14$
  • D
    $9$

Explore More

Similar Questions

$5$ men and $5$ women earn $Rs. 660$ in $3$ days. $10$ men and $20$ women earn $Rs. 3500$ in $5$ days. In how many days can $6$ men and $4$ women earn $Rs. 1060$?

$A$ and $B$ can do a work in $8$ days,$B$ and $C$ can do the same work in $12$ days. $A, B$ and $C$ together can finish it in $6$ days. $A$ and $C$ together will do it in (in days):

$S, T$ and $U$ can complete a work in $40, 48$ and $60$ days respectively. They received $Rs. 10800$ to complete the work. They begin the work together,but $T$ left $2$ days before the completion of the work and $U$ left $5$ days before the completion of the work. $S$ completed the remaining work alone. What is the share of $S$ (in $Rs.$) from the total money?

Difficult
View Solution

Shashi can do a piece of work in $20$ days. Tanya is $25\%$ more efficient than Shashi. The number of days taken by Tanya to do the same piece of work is

$A$ and $B$ can complete a piece of work in $18$ days; $B$ and $C$ in $24$ days; $C$ and $A$ in $36$ days. $A$ alone can complete the work in (in days):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo