$150$ workers were engaged to finish a job in a certain number of days. $4$ workers dropped out on the second day,$4$ more workers dropped out on the third day,and so on. It took $8$ more days to finish the work. Find the number of days in which the work was completed.

  • A
    $25$
  • B
    $26$
  • C
    $27$
  • D
    $28$

Explore More

Similar Questions

If for an arithmetic progression $S_{2n} = 2S_n$,then $S_{3n} / S_n = \dots$

Let $a_1, a_2, \ldots, a_{2024}$ be an Arithmetic Progression such that $a_1 + (a_5 + a_{10} + a_{15} + \ldots + a_{2020}) + a_{2024} = 2233$. Then $a_1 + a_2 + a_3 + \ldots + a_{2024}$ is equal to . . . . . .

The sequence $\log a, \log \frac{a^2}{b}, \log \frac{a^3}{b^2}, \ldots$ is

The $p^{\text{th}}$,$q^{\text{th}}$,and $r^{\text{th}}$ terms of an $A.P.$ are $a$,$b$,and $c$ respectively. Show that $(q-r)a + (r-p)b + (p-q)c = 0$.

Difficult
View Solution

If $1, \log _9(3^{1-x}+2), \log _3(4 \cdot 3^x-1)$ are in $A.P.$,then $x$ equals

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo