If $A$ and $B$ together can complete a work in $18$ days,$A$ and $C$ together in $12$ days,and $B$ and $C$ together in $9$ days,then $B$ alone can do the work in (in days)

  • A
    $18$
  • B
    $24$
  • C
    $30$
  • D
    $40$

Explore More

Similar Questions

$A$ can do a work in $10 \text{ days}$ and $B$ in $20 \text{ days}$. If they work together on it for $5 \text{ days}$,then the fraction of the work that is left is:

Difficult
View Solution

$A$ and $B$ working separately can do a piece of work in $9$ and $12$ days,respectively. If they work for a day alternatively with $A$ beginning,the work would be completed in (in days):

$A$ can do a work in $12 \, days$. When he had worked for $3 \, days$,$B$ joined him. If they complete the work in $3$ more $days$,in how many $days$ can $B$ alone finish the work?

Difficult
View Solution

If the wages of $45$ women amount to $Rs. 46575$ in $48$ days,how many men must work for $16$ days to receive $Rs. 17250$,given that the daily wage of a man is double that of a woman?

$10$ men can complete a piece of work in $15$ days and $15$ women can complete the same work in $12$ days. If all the $10$ men and $15$ women work together,in how many days will the work get completed?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo