Anu can complete a work in $10$ days. Manu is $25\%$ more efficient than Anu,and Sonu is $60\%$ more efficient than Manu. Working together,how long would they take to finish the job? (in days)

  • A
    $3 \frac{5}{8}$
  • B
    $5 \frac{6}{7}$
  • C
    $2 \frac{6}{17}$
  • D
    None of these

Explore More

Similar Questions

$45$ men complete a piece of work in $30$ days working $12$ hours a day. In how many days will $60$ men complete the work working $10$ hours a day?

$A$ can do a piece of work in $16$ days and $B$ in $24$ days. They take the help of $C$ and all three together finish the work in $6$ days. If the total remuneration for the work is $Rs. 400$,what is the amount (in $Rs.$) each will receive in proportion to the work done?

Difficult
View Solution

If $12$ men or $18$ women can build a wall in $14$ days,then working at the same rate,$8$ men and $16$ women can build the same wall in how many days?

$A$ work can be completed by $P$ and $Q$ in $12$ days,$Q$ and $R$ in $15$ days,and $R$ and $P$ in $20$ days. In how many days can $P$ alone finish the work?

Difficult
View Solution

$A$ can do a work in $20 \, days$ and $B$ in $40 \, days$. If they work on it together for $5 \, days$,then the fraction of the work that is left is:

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo