$A$ takes $10\, \text{days}$ less than the time taken by $B$ to finish a piece of work. If both $A$ and $B$ can do it in $12\, \text{days}$, then the time taken by $B$ alone to finish the work is (in $\text{days}$)

  • A
    $30$
  • B
    $27$
  • C
    $20$
  • D
    $25$

Explore More

Similar Questions

$A$ and $B$ together can complete a work in $12$ days. $A$ alone can complete it in $20$ days. If $B$ does the work only for half a day daily,then in how many days will $A$ and $B$ together complete the work?

$A$ man is twice as fast as a woman and a woman is twice as fast as a boy in doing a work. If all of them, a man, a woman and a boy, can finish the work in $7$ days, in how many days will a boy do it alone?

$A$ can do a work in $10 \text{ days}$ and $B$ in $20 \text{ days}$. If they work together on it for $5 \text{ days}$,then the fraction of the work that is left is:

Difficult
View Solution

$A, B$ and $C$ are employed to do a piece of work for $Rs. 575$. $A$ and $C$ are supposed to finish $\frac{19}{23}$ of the work together. The amount to be paid to $B$ is (in $Rs.$)

$A$ can do a piece of work in $8$ days. $A$ undertook it for $Rs. 320$. With the help of $B$,he finishes the work in $6$ days. $B$'s share is (in $Rs.$):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo