$A$ contract is to be completed in $50 \text{ days}$ and $105 \text{ men}$ were set to work,each working $8 \text{ hours a day}$. After $25 \text{ days}$,$\frac{2}{5}$ of the work is finished. How many additional men must be employed so that the work may be completed on time,with each man now working $9 \text{ hours a day}$?

  • A
    $34$
  • B
    $36$
  • C
    $35$
  • D
    $37$

Explore More

Similar Questions

$A, B$ and $C$ can do a piece of work in $20, 30$ and $60$ days respectively. In how many days can $A$ do the work if he is assisted by $B$ and $C$ on every third day?

Difficult
View Solution

$A$ and $B$ can do a piece of work in $12$ days and $15$ days,respectively. They began to work together,but $A$ left after $4$ days. In how many more days would $B$ alone complete the remaining work?

$7$ men can complete a piece of work in $12$ days. How many additional men will be required to complete double the work in $8$ days?

Difficult
View Solution

$A$ daily-wage labourer was engaged for a certain number of days for $Rs. 5,750$ but being absent on some days he was paid only $Rs. 5,000$. What was his maximum possible daily wage? (in $Rs.$)

$A$ and $B$ can complete a piece of work in $30 \text{ days}$,$B$ and $C$ can complete the same work in $20 \text{ days}$,and $A$ and $C$ can complete it in $15 \text{ days}$. If all of them work together,the time taken to complete the work will be? (in $days$)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo