$A$ can finish a work in $12$ days and $B$ can do it in $15$ days. After $A$ had worked for $3$ days,$B$ also joined $A$ to finish the remaining work. In how many days will the remaining work be finished?

  • A
    $5\frac{1}{2}$
  • B
    $4\frac{1}{2}$
  • C
    $5$
  • D
    $6$

Explore More

Similar Questions

$A$ and $B$ working separately can do a piece of work in $9$ and $12$ days,respectively. If they work for a day alternately with $A$ beginning,the work would be completed in (in days):

Nikita,Nishita,and Kavita can complete a work in $2 \frac{2}{3}$ days. If Nishita and Kavita can complete it in $4$ days,and Nishita alone can do it in $6$ days,then in how many days can Nikita and Nishita complete the work?

If $6$ men and $8$ boys can do a piece of work in $10$ days and $26$ men and $48$ boys can do the same work in $2$ days,the time taken by $15$ men and $20$ boys to do the same type of work will be (in days)

$40$ men can complete a work in $40$ days. They started the work together. But at the end of each $10^{th}$ day,$5$ men left the job. The work would have been completed in (in days):

$A$ certain sum of money is sufficient to pay wages for $21$ days of $X$ or $28$ days of $Y$. The money is sufficient to pay the wages of both for ........ days.

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo