$A$ and $B$ can complete a piece of work in $45$ and $40$ days,respectively. They began the work together,but $A$ leaves after some days and $B$ completed the remaining work in $23$ days. After how many days did $A$ leave?

  • A
    $6$
  • B
    $8$
  • C
    $9$
  • D
    $12$

Explore More

Similar Questions

$18$ women can complete a work in $12$ days and $12$ men can complete the same work in $9$ days. In how many days will $8$ men and $8$ women complete that work? (in days)

$A$ can do a certain work in the same time in which $B$ and $C$ together can do it. If $A$ and $B$ together could do it in $10 \text{ days}$ and $C$ alone in $50 \text{ days}$,then $B$ alone could do it in (in $\text{days}$):

Difficult
View Solution

$A, B$ and $C$ can complete a work in $2 \, h$. If $A$ does the job alone in $6 \, h$ and $B$ in $5 \, h$,how long will it take for $C$ to finish the job alone? (in $h$)

$A$ group of men decided to do a work in $10 \, days,$ but five of them absented themselves. If the rest of the group finished the work in $12 \, days,$ find the original number of men? (in $men$)

$A$ daily-wage labourer was engaged for a certain number of days for $Rs. 5,750$ but being absent on some days he was paid only $Rs. 5,000$. What was his maximum possible daily wage? (in $Rs.$)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo