$X$ and $Y$ can do a piece of work in $20$ days and $12$ days respectively. $X$ started the work alone and then after $4$ days $Y$ joined him until the completion of the work. How long did the work last? (in days)

  • A
    $6$
  • B
    $10$
  • C
    $15$
  • D
    $20$

Explore More

Similar Questions

$A$ and $B,$ working separately,can complete a piece of work in $9$ and $12$ days,respectively. If they work for a day alternately,$A$ beginning,in how many days will the work be completed?

$A$ can do a work in $10 \text{ days}$ and $B$ in $20 \text{ days}$. If they work together on it for $5 \text{ days}$,then the fraction of the work that is left is:

Difficult
View Solution

$A$ and $B$ can complete a piece of work in $12$ and $18 \text{ days}$ respectively. $A$ begins to do the work and they work alternatively one at a time for $1 \text{ day}$ each. The whole work will be completed in (in $\text{days}$):

$A$ alone would take $27 \, \text{days}$ more to complete the job than if both $A$ and $B$ worked together. If $B$ worked alone, he would take $3 \, \text{days}$ more to complete the job than $A$ and $B$ working together. What time would they take if both $A$ and $B$ worked together? (in $\text{days}$)

$10$ men can complete a piece of work in $15$ days and $15$ women can complete the same work in $12$ days. If all the $10$ men and $15$ women work together,in how many days will the work get completed?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo