$P, Q$ and $R$ can finish a work in $10, 12$ and $15$ days respectively. If $Q$ stops after $2$ days,how long would it take $P$ and $R$ to finish the remaining work? (in days)

  • A
    $6$
  • B
    $4$
  • C
    $3$
  • D
    $2$

Explore More

Similar Questions

$18$ women can complete a work in $12$ days and $12$ men can complete the same work in $9$ days. In how many days will $8$ men and $8$ women complete that work? (in days)

$A$ and $B$ together can complete a piece of work in $12$ days and $B$ and $C$ together in $15$ days. If $A$ is twice as good a workman as $C$,then in how many days will $B$ alone complete the same work?

Difficult
View Solution

$5$ men and $5$ women earn $Rs. 660$ in $3$ days. $10$ men and $20$ women earn $Rs. 3500$ in $5$ days. In how many days can $6$ men and $4$ women earn $Rs. 1060$?

$250$ men can finish a work in $20 \, \text{days}$ working $5 \, \text{hours}$ a day. To finish the work within $10 \, \text{days}$ working $8 \, \text{hours}$ a day,the minimum number of men required is:

$A$ can do a work in $20 \, days$ and $B$ in $40 \, days$. If they work on it together for $5 \, days$,then the fraction of the work that is left is:

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo