$10$ men working $6\, \text{h}$ a day can complete a work in $18\, \text{days}$. How many $\text{hours per day}$ must $15$ men work to complete the same work in $12\, \text{days}$?

  • A
    $6$
  • B
    $10$
  • C
    $12$
  • D
    $15$

Explore More

Similar Questions

$5$ men can prepare $10$ toys in $6$ days working $6$ hours a day. Then,in how many days can $12$ men prepare $16$ toys working $8$ hours a day? (in days)

$A$ and $B$ can do a piece of work in $12$ days, $B$ and $C$ in $8$ days, and $C$ and $A$ in $6$ days. How long would $B$ take to do the same work alone? (in days)

Difficult
View Solution

$A$ and $B$ working separately can do a piece of work in $10 \text{ days}$ and $15 \text{ days}$ respectively. If they work on alternate days beginning with $A$,in how many days will the work be completed?

$A$ can do a piece of work in $14$ days,which $B$ can do in $21$ days. They begin together,but $3$ days before the completion of the work,$A$ leaves. The total number of days to complete the work is:

Difficult
View Solution

$A, B$ and $C$ can do a piece of work individually in $8, 10$ and $15$ days respectively. $A$ and $B$ start working,but $A$ quits after working for $2$ days. After this,$C$ joins $B$ until the completion of the work. In how many days will the work be completed?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo